PowerPal™ T2 Turgo 1                                                                                                                                                                                                                                                                                                               
                    
                    Inhaltszusammenfassung zur Seite Nr. 2 
                    
                        READ THIS FIRST    This manual contains important information concerning your new PowerPal T2 Turgo  micro-hydroelectric generator. It covers Model MHG-T2. You should read this  manual carefully before installing PowerPal or allow a trained technician from your  local PowerPal Service Center to install it for you.     Your PowerPal generator is designed to be simple to operate and easy to maintain. If  used in accordance with these instructions your PowerPal will give you many years of  service.
                    
                    Inhaltszusammenfassung zur Seite Nr. 3 
                    
                        POWERPAL COMPONENTS    Inside your PowerPal box you will find:    • 1 x generator-turbine assembly  • 1 x penstock adaptor flange, internal diameter 110mm  • 1 x rubber gasket  • 4 x M10 foundation nuts and bolts  • 1 x control panel including electronic load controller  • 1 x ballast load  • 1 x Guarantee Card  • 1 x this instruction manual.    Please advise immediately if any parts are missing. Complete your Guarantee Card  and have it signed by your PowerPal dealer.     The PowerPal system co
                    
                    Inhaltszusammenfassung zur Seite Nr. 4 
                    
                                              A. Forebay, or water    tank   B  B. Atmospheric vent    A C. Penstock, or intake    pipe    D. Spear valve    E. Turbine                Forebay    C         F   Turbine stand  D lt E G PowerPal™ T2 Turgo 4                                                                                                                                                                                                                                                                                
                    
                    Inhaltszusammenfassung zur Seite Nr. 5 
                    
                        SELECTING A SITE    PowerPal is designed for use in a wide range of locations. There are two critical  factors that influence power output – head and flow. Head is the vertical distance  between the turbine and the water source (forebay), measured in meters. Flow is the  amount of water that passes through the turbine at any instant, measured in litres per  second (l/sec).     See Page 17 for detailed head, flow rate and output data for the three T2 models.        Measuring Gross Head    The gro
                    
                    Inhaltszusammenfassung zur Seite Nr. 6 
                    
                        Measuring Flow    The best way to measure the water flow is to take a piece of pipe the same diameter as  the penstock, insert it in the stream or dam where the flow is expected to come from,  and measure the flow from there.     In the diagram below, a short length of pipe (less than 1 meter) is buried into the side  of a small ‘dam’ using mud or improvised sandbags. The top end of the pipe is  completely submerged and part of the normal stream flow is diverted through the  pipe. When this is f
                    
                    Inhaltszusammenfassung zur Seite Nr. 7 
                    
                                                        A B    The penstock is shown by the black line    A-B. In the first diagram (A) the penstock    follows the stream. This may lead to    unnecessary length and cost. In diagram    B, the most direct route is selected to   reduce length and cost. Diagram C shows    the best alternative where a side channel    or ‘power conduit’ is cut into the side of    the hill. This carries the water to a point    as close to above the turbine as possible   and best reduces the l
                    
                    Inhaltszusammenfassung zur Seite Nr. 8 
                    
                          SYSTEM INSTALLATION    Mechanical Aspects    After locating a suitable site and completing the civil works, your PowerPal is ready  for installation. To do this:    1. Bolt the turbine to a turbine stand or base which allows at least 300mm clearance  between the turbine and the ground. This clearance is required to prevent  splashback that will disrupt turbine performance. The turbine stand should be  made from concrete with the four M12 foundation bolts embedded. Bolt spacing  is shown in the
                    
                    Inhaltszusammenfassung zur Seite Nr. 9 
                    
                            hydro Main network or house  220VAC  distribution board house supply    turbine          Electronic Load    Ballast load  Controller - ELC                              A B C        To connect the electrical components, please follow these steps:      The electrics should be installed by persons competent in mains voltage    wiring. This system operates on a switched neutral basis. Neutral and phase   connections to the load elements should be treated as live at all times!    1. Install the c
                    
                    Inhaltszusammenfassung zur Seite Nr. 10 
                    
                          4. Connect the user load cables L1 and L2 between the control box and the house.    5. Connect the ballast load (C) to the control box and user load cable. The ballast  load is rated 10-15% (maximum) higher than the rated power output of the  generator e.g. 2.2kW for model MHG-T2. As such, it will become hot, up to  100°C. To prevent injury and the risk of fire, the ballast load must be installed in a  safe place and preferably in an additional enclosure.     6. Close the generator terminal bo
                    
                    Inhaltszusammenfassung zur Seite Nr. 11 
                    
                        5. Operate like this for 15 minutes while observing any unusual noise, excessive  temperature or other problems and if OK then switch on the power to the user. Up  till now the ballast load has been receiving all the power and should be hot, but  once switching on the user load the power to the ballast load will fall.     6. The voltage should remain stable as loads are switched on or off. If the voltage  falls below 220V then check the water flow conditions. The voltage may need to  be checked 
                    
                    Inhaltszusammenfassung zur Seite Nr. 12 
                    
                        Changing the Bearings and Seal    Apart from greasing the bearing, there are only two tasks that must be completed at  regular intervals. These are the changing of the lower generator bearing & turbine  bearing and the lower bearing seal every two years. See the section on Technical  Specifications at the end of this manual for part numbers. These are commonly  available in most countries but if in doubt contact your dealer. To replace the bearings  and seal, follow these steps:     1. Shut down
                    
                    Inhaltszusammenfassung zur Seite Nr. 13 
                    
                                              A B                           C D                           E F       TROUBLESHOOTING    If any problems are encountered, check this section before contacting your Service  Center.    1. Head and flow conditions appear to be OK, but PowerPal will not work.    It is likely that the system has been installed incorrectly. Check this by following the  steps once more.    PowerPal™ T2 Turgo 13                                                                                       
                    
                    Inhaltszusammenfassung zur Seite Nr. 14 
                    
                        2. PowerPal has provided electricity for a while and suddenly the electricity stops.    If this instruction manual is not followed and power consumption is too high, or if  there is a short circuit in an appliance the circuit breaker in the electronic load  controller will trip. This will stop the electric current. If this occurs, check for possible  causes and rectify. Reset the switch on the circuit breaker to the ‘on’ position.     3. Voltage is 220V under zero-load conditions but falls when 
                    
                    Inhaltszusammenfassung zur Seite Nr. 15 
                    
                        a) Start the generator and adjust the spear valve to obtain 220-240 volts, 0 amps at the  panel. [Do not turn the circuit breaker on].  b) Adjust the potentiometer on the circuit board very slowly to the left. When you  detect a small decrease in voltage, stop. Turn on the circuit breaker and increase water  to increase power to the unit. Increase power until a load of 2kW is indicated (P =VI).  c) If adjusting the potentiometer does not correct the problem, then contact PowerPal.  The problem i
                    
                    Inhaltszusammenfassung zur Seite Nr. 16 
                    
                        APPENDIX A – FOREBAY DESIGN    The instructions given on page 7 of this manual to design the forebay are adequate for  most cases. The most important aspects of forebay design are:    1) To allow a continual flow of water to the penstock so that the turbine keeps  functioning.  2) To have sufficient safeguards to prevent sand, vegetation and other debris  from entering the penstock which could cause blockages and disrupt the  turbine. This includes a safety aspect to keep away children and anima
                    
                    Inhaltszusammenfassung zur Seite Nr. 17 
                    
                        POWERPAL T2 TURGO MODELS    T-2 Model (1.5kW) (single nozzle)        Output (watts) H (head, in metres) 14 15 16 17 18 19 20     Q (flowrate, in l/sec) 18.5 17.3 16.215.214.413.612.9   1250   18.5 17.316.315.414.613.9   1361    18.517.416.515.614.8   1452     18.517.516.615.7   1543      18.517.516.6   1633       18.517.6   1724        18   1750                           T-2 Model (2.0kW Med H) (single nozzle)        Output (watts) H (head, in metres) 16 17 18 19 20       Q (flowrate in l/sec) 2